Plaza Live Construction Photographs
20150403_03.JPG

04/03/2015 #03 - Here is the wall completed to five feet. Note the overlapping rebar which has been laid in the cinderblock channels to enhance the strength of the wall. Before continuing with the wall, additional rebar will be installed vertically every four feet down into the cells and be tied to the rebar that extends into the wall from the footings, then the channel will be filled with concrete. This rebar will extend into the next section of wall.